Hospitality · Development mandate

Turks & Caicos — Third Turtle Resort & Marina

Operator requirements, international design teams and island infrastructure coordinated before delivery.

Place
Turks and Caicos
Portfolio chapter
2014–2019
Stage reached
Development preparation
Role
Operating Manager and Design-Builder representative
Third Turtle Resort & Marina proposed arrival. Project concept visualisation.

I worked on the owner-side development and technical coordination of Third Turtle Resort & Marina.

Third Turtle Resort & Marina brought together a resort site of approximately 6.88 ha, Waldorf Astoria / Hilton requirements and an international consultant team. The September 2017 programme proposed 140 keys.

The mandate connected architecture, structure and building services with food and beverage, public spaces, environmental assessment, local infrastructure, logistics and cost planning. Hilton required MARKZEFF for guest-room interiors; the project team was to coordinate with the studio.

Detailed Development Permission was granted on 11 May 2018. The case presents development preparation and operator/design coordination. Resort images are proposals, not photographs of a completed hotel.

Project credits
Proposed resort architecture: Officina Architetti / Hembert Peñaranda. Project archive imagery.