← All work

Infrastructure · Technical delivery

Berth 10, Yuzhny — port development into execution

I led technical and portfolio governance for Berth 10 at Yuzhny, taking a port-development programme into execution.

Place
Ukraine
Portfolio chapter
Marine & port
Stage reached
Implementation commenced, then stopped
Role
Technical and portfolio governance
Yuzhny project-area context. Archive photograph.

The Berth 10 cargo-terminal programme planned annual throughput of 1.2 million tonnes. It joined operational-basin dredging and land reclamation with sheet-pile and steel-pile structures, anchoring, reinforced concrete, utilities and upper works. The task connected the formation of land and marine access with the structures and services required for the terminal.

My work brought these interdependent activities into one execution framework. Production planning, equipment reports, executed-work records and commercial schedules supported control across the marine and land-based work.

Implementation commenced, then stopped following changes in the country’s domestic political environment. The throughput figure describes the planned terminal; the result presented is mobilisation and execution, rather than a completed berth.

Project credits
Retained project-area and mobilisation photography.