Residential mobilisation — a 306-apartment development

I led technical and portfolio work taking a 306-apartment development from early works into construction.

Place
Ukraine
Portfolio chapter
2010–H1 2014
Stage reached
Construction during the mandate
Role
Technical leadership — mobilisation and construction
Residential site: excavation, pile heads and early structural works. Construction-report photograph, 2012.

The residential project comprised a 21,402 m² programme and 306 apartments. The mandate-period work moved through demolition and excavation into structural construction.

I connected mobilisation and construction progress with the platform’s technical and funding control. This case shows the point at which a development proposition had to become a working site, with the companies, resources and reporting needed to sustain delivery.

The project was in construction during my mandate. The dimensions follow the 2013 programme; later completion belongs to a subsequent period.