I led the businesses that engineered and delivered a 5,042-plate kinetic façade for Odesa’s sea terminal.
Place
Ukraine
Portfolio chapter
2014–2019
Stage reached
Specialist package delivered
Role
Company leadership — kinetic façade engineering and delivery
The sea-terminal installation turns moving aluminium plates into a large kinetic surface. Its specification covered 5,042 plates; an independent support structure carries the installation’s loads rather than transferring them to the existing building.
FES delivered the specialist envelope and Tech Facade developed the detailed design and production information. My company-leadership remit connected the engineering product with manufacturing and delivery, including the relationship between the moving surface, its modules and the supporting frame.
The delivered installation demonstrates the translation of an unusual architectural requirement into a buildable specialist system.
In motion
Odesa passenger terminal: the kinetic façade in motion. FES project archive film; original soundtrack.
Odesa sea terminal — panels moving in the wind
Odesa sea terminal — movement of the kinetic panels under wind. FES project archive film · 1:54 · 4K · original soundtrack.
Marine passenger terminal: the broad kinetic façade and independent support from the forecourt. FES project photograph.Marine passenger terminal: oblique view of the kinetic envelope against the port basin. FES project photograph.Marine passenger terminal: the façade, forecourt and pier viewed from the sea side. FES project photograph.Odesa sea terminal — Front elevation during construction of the independent facade support frame. Project archive photograph.Odesa sea terminal — Lifting and assembling a vertical section of the independent steel frame. Project archive photograph.Odesa sea terminal — Steel facade frame and work platforms viewed from the forecourt. Project archive photograph.Odesa sea terminal — Crane operations beside the facade frame during installation. Project archive photograph.Odesa sea terminal — The end of the steel frame during crane-assisted installation. Project archive photograph.Odesa sea terminal — Steel frame and scaffolding viewed along the terminal forecourt. Project archive photograph.Odesa sea terminal — A corner of the facade frame and temporary working platforms. Project archive photograph.Odesa sea terminal — The facade frame and scaffolding illuminated during night work. Project archive photograph.Odesa sea terminal — Installation of kinetic panels across the facade, with temporary scaffolding. Project archive photograph.Odesa sea terminal — Kinetic aluminium panels viewed from below. Project archive photograph.Odesa sea terminal — Space between the terminal and the independent support structure. Project archive photograph.Odesa sea terminal — Steel connections and kinetic panels viewed from behind the facade. Project archive photograph.
Project credits Retained FES / Tech Facade project records. Architecture and interiors by the respective project designers. Proposed views are identified in image captions.